What Was Announced at Taloja and Why the Structure Matters for Insurance
CoreWeave is entering India with 240 MW of capacity at AdaniConneX's Taloja campus in Navi Mumbai, according to Inc42's report of 8 October 2026. The capacity sits in three buildings of 80 MW each, CoreWeave will be the sole tenant, and the deal carries an option for a further 240 MW. AdaniConneX is a 50:50 joint venture between Adani Enterprises and EdgeConneX, and Adani announced in February a plan to invest $100 billion in renewable-powered AI data centres by 2035.
The first phase is expected to be operational by mid-2028. CoreWeave plans to deploy NVIDIA's Vera Rubin platform with direct liquid cooling in the GPU halls, supported by a non-evaporative chilled-water system.
For insurers and brokers, the headline number matters less than the shape of the deal. A multi-tenant colocation hall spreads risk across dozens of customers, each with modest equipment values and its own contract. A sole-tenant AI campus does the opposite. One landlord owns the shell, the power train and the cooling plant. One tenant owns GPU racks whose value per rack is far higher than a conventional server cage. Each party's revenue depends almost entirely on the other's assets staying up.
That mutual dependence is what this post is about: how a lease of this kind should split property cover, machinery breakdown on the cooling plant, waivers of subrogation, contingent business interruption, and construction-phase cover through to go-live. The same questions apply, at smaller scale, to any Indian GCC or enterprise that rents dedicated AI capacity.
Who Owns What: The Demarcation Line in a Single-Tenant AI Campus
Start with ownership, because Indian property policies follow insurable interest. In a typical powered-shell or build-to-suit arrangement the split looks like this:
- Landlord (developer/operator): land, building shell, structural works, electrical substations and HV/LV distribution, transformers, UPS and battery rooms, generators, the chilled-water plant, primary cooling loops and fire detection and suppression.
- Tenant (GPU cloud provider): GPU servers and racks, networking fabric, storage, in-rack or row-level cooling hardware it procures, and customer-specific fit-out.
- Contested zone: coolant distribution units (CDUs), secondary liquid loops, manifolds and quick-disconnects that connect the facility water system to the racks.
The contested zone is where most disputes start. With direct liquid cooling, the boundary between "building services" and "IT equipment" is a pipe joint inside the hall. If the lease does not name who owns and maintains each CDU and each secondary loop, neither party can be confident its policy responds when a leak or pump failure damages racks.
Once ownership is fixed, each side can buy the right first-party cover: the landlord a property insurance or industrial all-risks programme on shell and plant, the tenant an all-risks or electronic equipment insurance cover on its hardware at current replacement cost.
Machinery Breakdown and the Liquid-Cooling Plant
Fire is the peril people picture, but in a liquid-cooled GPU hall the more frequent loss is mechanical or electrical breakdown: a CDU pump fails, a control board in the chilled-water plant trips, a heat exchanger fouls, or a valve sticks. Standard fire and all-risks wordings in India generally exclude mechanical and electrical breakdown of the plant itself, which is why a separate machinery breakdown policy (and its loss-of-profits companion) exists.
For the landlord, the machinery breakdown schedule should list the chilled-water plant, CDUs it owns, pumps, heat exchangers, switchgear, transformers, UPS modules and generators, each at reinstatement value. Underwriters will ask about redundancy (N+1 or 2N on pumps and CDUs), spare holdings, and the lead time for replacement units, because these drive how long an outage lasts.
For the tenant, the question is different. A CDU breakdown on the landlord's side may cause no physical damage to GPUs at all, only a thermal shutdown. That is a pure loss of revenue with no damage to tenant property, so the tenant's own property policy will not respond. It falls to contingent cover or to the lease (see the business interruption section below).
Leak damage from a landlord-owned loop
Where a landlord-owned secondary loop leaks onto tenant racks, the damage to racks is tenant property damaged by a landlord asset. The tenant's all-risks cover should respond to water or coolant damage without an exclusion for leakage from the insured's own or another party's systems. The tenant's insurer will then look to recover from the landlord unless the lease waives that right. Our post on advanced cooling risk in Indian data centres covers the underwriting questions on coolant chemistry and leak detection in more detail.
Waiver of Subrogation: Stopping Two Insurers From Suing Each Other
In a sole-tenant campus, almost every serious loss involves an asset owned by one party damaging or shutting down the other. Without a waiver, the tenant's insurer pays for the damaged racks and then exercises subrogation against the landlord, the landlord's liability insurer defends, and the commercial relationship absorbs the friction for years.
A mutual waiver of subrogation in the lease, matched by an endorsement on each party's property policy, prevents this. The structure that usually works:
- Each party agrees to insure its own property for full replacement value.
- Each party waives claims against the other for loss to its property to the extent it is insured, or would have been insured had it complied with the lease.
- Each party obtains an endorsement from its insurer permitting that waiver, so the insurer cannot argue the insured prejudiced its recovery rights.
The third step is the one most often missed. An Indian property policy will typically carry a condition protecting the insurer's subrogation rights. If the insured signs a waiver without the insurer's consent, the insurer may argue its position has been prejudiced. Brokers should obtain the endorsement before the lease is signed, not after the first claim.
The general mechanics are the same as in conventional commercial leases, which we cover in lease agreement insurance clauses for landlords and tenants. What changes at Taloja scale is the value at stake: the tenant's GPU equipment inside an 80 MW building could well be worth more than the building shell that houses it.
Business Interruption Runs Both Ways
Business interruption is where single-tenant dependence becomes most visible.
Landlord BI. The landlord's income is rent and service charges from one tenant. If a fire damages a building and the lease lets rent abate during repair, the landlord loses that income. A loss-of-rent or business interruption section on the landlord's property programme covers this, with an indemnity period long enough to rebuild an 80 MW building and re-procure long-lead electrical plant. If the lease does not provide for rent abatement, the risk sits with the tenant instead, and the landlord's BI exposure is lower.
Tenant BI. The tenant's income comes from selling GPU capacity to its own customers. It can lose that income in three ways:
- Damage to its own racks (covered by its own BI linked to its own property cover).
- Damage to landlord plant that causes an outage without touching tenant equipment (needs contingent BI or a specific extension).
- Failure of utilities to the campus, such as grid power or water supply (needs a public utilities or suppliers' extension).
Contingent BI for the second scenario is the cover most often left out. The tenant should name the landlord's premises and plant as a specified supplier or "premises of others" under its BI section, with physical loss or breakdown at the landlord's plant as the trigger. Insurers will want details of redundancy and the landlord's maintenance regime before pricing it.
Lease service credits are not BI cover
AI capacity leases often include availability commitments and service credits. A service credit reduces what the tenant pays; it does not replace the revenue the tenant loses from its own customers. Tenants should size contingent BI on their own gross profit at risk, not on the value of credits receivable. The third-party data centre operator risk profile sets out how service credits interact with operator liability in the multi-tenant setting.
Construction Phase Through the Mid-2028 Go-Live
None of CoreWeave's Taloja capacity is operational yet. Between now and the expected mid-2028 first-phase go-live, the risk sits in construction, erection and commissioning, and the insurance programme needs to hand over cleanly to the operating covers.
Landlord construction cover. A contractors' all risks policy on civil works and an erection all risks policy on electrical and mechanical plant, with a delay-in-start-up (DSU) or advance loss of profits section protecting the rent that should begin at handover. The testing and commissioning period, when chillers, CDUs and power trains are run up under load for the first time, deserves particular attention in the policy wording.
Tenant fit-out and equipment. GPU racks arriving at site are high-value, theft-attractive cargo. The tenant needs marine or transit cover through to installation, and then an erection or installation all-risks cover during rack integration and burn-in. The handover point between the landlord's EAR and the tenant's installation cover should match the physical demarcation in the lease.
Overlap risk. A loss during commissioning can involve the landlord's contractor, the landlord's EAR insurer, the tenant's installation insurer and the tenant's own engineers at once. A project-wide waiver of subrogation across both programmes, plus agreed rules on who has care, custody and control of each hall at each stage, reduces disputes. Our post on AI factory construction, EAR, DSU and GPU cargo walks through the construction-stage covers in detail.
What Indian GCCs and Enterprises Renting AI Capacity Should Ask
The World Bank's India Development Update, as reported by MediaNama on 8 October 2026, puts employment at India's global capability centres at 2.36 million in 2025, up from 1.9 million in 2024. As more of these centres and Indian enterprises buy dedicated GPU capacity, rather than generic cloud instances, they inherit a version of the same landlord-tenant problem one step removed. Their provider is the tenant; the campus owner is a party they have no contract with.
Questions worth putting to an AI capacity provider before signing:
- Who owns the cooling and power plant serving the halls your workloads run in, and what redundancy does it have?
- Does the provider carry contingent BI that responds to an outage at the landlord's plant, and does your contract give you any remedy beyond service credits?
- If your organisation places its own hardware or storage on the provider's racks, is that equipment covered by the provider's policy, or must you insure it yourself?
- Is there a waiver of subrogation chain from the landlord to the provider to you, or could the provider's insurer pursue you for damage caused by your own equipment?
- Where does your data sit if a hall is down for months, and is failover to another site part of the contract?
On the buyer side, a GCC or enterprise should check whether its own BI programme can name the AI capacity provider as a dependency. Many Indian BI wordings restrict contingent cover to named suppliers and customers with physical premises; a cloud provider may need specific wording. Losses from pure service failure without physical damage are a separate question, closer to technology or cyber insurance than property.
A Working Checklist for Brokers on Both Sides
For brokers advising the landlord or the tenant in a single-tenant AI campus, the practical sequence is:
- Fix the demarcation schedule first. List every CDU, loop and switchboard by owner before placing any cover.
- Match sums insured to the schedule. Landlord on shell and plant at reinstatement value; tenant on GPU racks at current replacement cost, reviewed as hardware generations change.
- Add machinery breakdown on both sides where each owns plant, with loss-of-profits sections.
- Paper the subrogation waiver in both the lease and both policies, and keep its scope within what is insured.
- Buy contingent BI for the tenant on landlord plant, and loss-of-rent cover for the landlord if the lease allows rent abatement.
- Align construction covers with the operating handover, so there is no gap between the end of EAR/DSU and the start of property and BI cover.
- Exchange certificates of insurance annually and reconcile them against the lease covenants.
None of this depends on the specifics of the Taloja transaction, whose lease terms are not public. It is the minimum structure any sole-tenant AI campus in India should have in place before the first rack is powered on.