What happened at Dhulkot, and what is still unknown
On Sunday 27 September 2026, at around 3 pm, a three-storey building under construction at Dhulkot village in Ambala, Haryana, collapsed. The Daily Pioneer reported on 28 September that at least six people died and 13 were pulled out of the debris. NDRF, SDRF and fire services worked the site. Reports compiled over 27 and 28 September put the number of labourers working there at about 35 to 40.
Ambala SP Ajit Singh Shekhawat said legal action would follow if negligence is found. The SDM said the owner and the contractor left the site after the collapse, and that the legality of the construction and its documents were being verified.
That is the full public record so far. The cause of the collapse has not been established, and this post does not speculate on it. What the incident does show, regardless of cause, is the claims position a small builder or labour contractor faces the morning after a structural failure: dead and injured workers, a destroyed structure, possible damage to neighbouring property, police scrutiny, and a dispute over who was the employer and who was in control of the site.
For most small sites in India, the honest answer to "what pays?" is very little, because the insurance was never bought or was bought in a form that does not respond. The rest of this post sets out the minimum stack, the exclusions that matter after a structural failure, and the paperwork that decides which party's policy (if any) is triggered.
Why small sites are usually uninsured or underinsured
Large infrastructure and commercial projects carry insurance because lenders, employers and public-sector contract conditions require it. A three-storey private building in a village on the edge of a district town usually has none of those pressures. The owner may be building for personal use or for rent, financed from savings. The contractor may be a labour contractor supplying gangs on a daily-wage basis, with materials bought by the owner.
In that structure, three gaps are common:
- No Contractors All Risk (CAR) policy at all. The owner assumes the contractor has cover. The contractor assumes the owner's property is the owner's problem.
- No Employees' Compensation (EC) policy, or one with a declared headcount far below the real number on site. A gang of 35 to 40 people on a Sunday can easily be double what was declared at inception.
- Workers who appear on no register. Daily-wage labour brought in through a sub-contractor or a mistri may not be on any muster roll, which makes identity, wage and employment proof difficult after an accident.
None of these gaps removes the liability. They only decide whether the liability is paid by an insurer or by the owner and contractor personally, and how long the families wait.
The minimum insurance stack for a small construction site
For a site of this size, the stack that actually responds to a collapse has three layers, with a fourth as a practical safety net.
- CAR policy with Section II third-party liability. Section I covers the works themselves (the structure, materials on site, and usually temporary works) against sudden and accidental physical loss, including collapse, on an all-risks basis subject to exclusions. Section II covers the insured's legal liability for bodily injury to, or property damage of, third parties arising out of the works. The CAR policy guide covers the wording in detail.
- Employees' Compensation policy. This covers the employer's statutory liability under the Employees' Compensation Act, 1923 for death or injury to workmen from accidents arising out of and in the course of employment. It is the policy that pays the families of workers who die on site. See the EC Act guide for how compensation is computed.
- Group Personal Accident (GPA) cover for workers who may not qualify cleanly under the EC policy, such as unregistered or casual labour, supervisors and family members of the contractor who help on site. GPA pays a fixed benefit on death or disablement without any need to prove employer liability. The GPA guide covers benefit design.
- Medical expenses extension on the EC policy, because the statutory compensation does not include hospital bills for the injured who survive, and 13 people rescued from debris will generate them.
The order matters for a small builder with a limited budget. If only one policy can be bought, EC comes first, because worker death is the largest and most certain liability. CAR with TPL comes second, because a collapse onto a neighbouring house, shop or passer-by creates a claim that has no statutory ceiling.
What Employees' Compensation pays after a collapse
The EC Act sets compensation by formula. For death, the employer pays 50% of the workman's monthly wages multiplied by the age-based relevant factor in Schedule IV, subject to a statutory minimum of INR 1,20,000. For permanent total disablement the figure is 60% of monthly wages times the relevant factor, subject to a minimum of INR 1,40,000. Funeral expenses are payable on top. Monthly wages are capped for the calculation at the ceiling notified by the central government, currently INR 15,000.
Compensation for death is not handed directly to families. Section 8 requires it to be deposited with the Commissioner for Employees' Compensation, who distributes it to dependants. If it is not paid within one month of falling due, Section 4A allows the Commissioner to impose interest at 12% a year and, where there is no justification for the delay, a penalty of up to 50% of the amount. Insurers generally pay compensation and interest, but the penalty is personal to the employer and is not recoverable under the policy. An owner and contractor who leave the site and delay the process are building their own uninsured penalty.
What CAR and GPA pay after a collapse
CAR Section I and Section II
Section I pays to reinstate the works lost in the collapse, up to the sum insured, less the deductible, subject to the exclusions discussed below. Debris removal is usually covered only if it was declared as a separate sum insured, and on a collapse it is a large cost.
Section II pays the insured's legal liability to third parties: a neighbour's damaged wall, a vehicle crushed on the road, a passer-by injured. It also typically pays defence costs incurred with the insurer's consent. Liability is subject to a per-occurrence limit, and on small sites that limit is often set at a nominal figure with no thought to the adjoining buildings.
Group Personal Accident
GPA pays the scheduled benefit (often a multiple of monthly wages, or a flat amount per person) on accidental death or disablement, regardless of fault and regardless of whether the EC claim succeeds. For families of unregistered workers this is often the only payment that arrives quickly.
The exclusions that defeat claims after a structural failure
A building collapse is exactly the kind of event in which the insurer's first question is "why did it fall?" The answer shapes coverage, which is why the investigation outcome matters even to an insured party.
Defective design and workmanship
Standard CAR wordings used in India exclude loss due to faulty design, and exclude the cost of replacing, repairing or rectifying defective material or workmanship. The workmanship exclusion is usually limited to the items immediately affected, so correctly executed parts of the works damaged by an accident caused by a defect remain covered. Where the cause is a design error, the standard exclusion can be much wider and can take out the entire collapse loss under Section I. Some markets offer extensions that narrow the design exclusion, but they are rarely bought on small private sites.
This does not usually affect EC. The EC Act is a no-fault statute: if the workman died from an accident arising out of and in the course of employment, compensation is payable whether the collapse was caused by bad design, bad concrete or bad luck.
Other CAR exclusions to check
- Wilful act or wilful negligence of the insured. Insurers will look at any evidence that warnings were ignored, such as visible cracks, unauthorised additional floors or removal of props too early.
- Removal or weakening of support under Section II. Damage to adjoining property from excavation or loss of support is often excluded unless an endorsement buys it back.
- Cessation of work. If the site was stopped for an extended period, cover may have lapsed or been restricted.
- Deviation from approved plans. Not a standard exclusion in itself, but an unapproved storey is a material change in risk, and non-disclosure lets the insurer contest the policy under the duty of utmost good faith.
Owner or contractor: the documents that decide liability
After the Ambala collapse, the SDM said the legality of the construction and its documents were being verified. The same documents decide which policy pays and who carries the uninsured remainder.
- The construction contract. It should say who is the principal, who is the contractor, who controls the site, who supplies materials and design, and who must insure. Without a written contract, the authorities and the insurer will infer roles from conduct, and the owner can end up treated as the employer.
- Sanctioned building plans and structural drawings. These establish whether the structure being built was the structure approved, and who prepared the design. They are also the first thing the CAR insurer will ask for.
- Muster rolls, attendance and wage records. These prove who was a workman, of whom, and at what wage. EC compensation is computed on monthly wages, so a missing wage record forces the Commissioner to estimate, and disputes slow the deposit.
- Insurance certificates from every contractor and sub-contractor, checked for the named insured, the site address, the period and the declared headcount.
Under Section 12 of the EC Act, where a principal employs a contractor to carry out work that is part of the principal's trade or business, the principal can be made liable to pay compensation to the contractor's workmen, with a right of indemnity against the contractor. The contract labour liability guide sets out how that chain works. For an owner building a property as part of a real estate or rental business, this is a live exposure. The protection is to name both owner and contractor on the CAR policy, with a cross-liability clause, and to require the contractor's EC policy to extend to the principal's liability under Section 12.
A practical checklist for small builders and labour contractors
The cost of this stack on a small site is modest relative to the exposure. The bigger cost is the discipline of keeping it accurate.
- Buy EC before the first worker arrives, on a declared headcount and wage roll that reflects peak, not average, deployment. Add a medical expenses extension.
- Buy CAR with Section II for the full contract value, with a separate sum insured for debris removal, a TPL limit sized to the adjoining buildings and road frontage rather than a nominal figure, and the owner, main contractor and sub-contractors named as insureds with a cross-liability clause.
- Add GPA for every person on site who might fall outside the EC roll, including casual labour, supervisors and family helpers.
- Keep a daily attendance register on site, signed, with names, ages and wage rates. Photograph it weekly.
- Endorse every change in scope, especially an added storey or a change in structural design, before the work starts.
- Notify all insurers immediately after an incident, deposit EC compensation with the Commissioner within one month, and stay engaged with the authorities. Leaving the site does not reduce liability; it adds penalty exposure and weakens the insured's position with every insurer involved.
Broker review of the CAR wording on design and workmanship exclusions, and of the TPL limit, takes an afternoon. It is the step most small builders skip, and it is the step that decides whether a collapse is an insured event or a personal debt. Sarvada's engineering insurance and workers' compensation pages cover how these products are placed.