Two fires, five weeks apart, and what each company disclosed
Two listed Indian electronics groups reported plant fires within five weeks of each other in 2026, and between them the disclosed losses add up to roughly Rs 66 crore.
The first was on 4 August 2026 at the Greater Noida unit of IL JIN Electronics (India), a subsidiary of Amber Enterprises. On 5 October 2026, Whalesbook reported that IL JIN had received a Rs 10 crore on-account payment from its insurers. The estimated loss is Rs 38.28 crore plus applicable GST, and the final assessment is still pending.
The second was on 9 September 2026 at the Kopparthy plant of AIL Dixon Technologies in YSR Kadapa, Andhra Pradesh, a subsidiary of Aditya Infotech. According to the company's exchange disclosure as reported by IndiaIPO, the fire started at about 8:15 am from a short circuit on the electrical power board in the assembly area. Estimated damage was about Rs 28 crore, covering raw materials, finished goods and testing equipment. The company said it had adequate insurance, had notified the insurer, and expected no disruption to overall operations. As reported alongside the disclosure, Aditya Infotech's shares closed 2.2% lower at Rs 3,743.15 on BSE.
We have already covered the Amber fire twice: once on customer-owned stock in contract manufacturing, and once on how listed companies word their fire disclosures. This post takes up three questions those posts did not:
- How an assembly-area power board becomes the ignition point, and which controls stop it.
- How raw material, work in progress and testing equipment are valued in an EMS claim, and where GST sits in that number.
- What a first interim cheque, about two months after the fire, tells you about where the claim stands.
A power board in the assembly area: electrical fire controls for EMS lines
The Kadapa fire began in about the most common place an electronics assembly fire can start. Assembly halls carry dense electrical load: SMT lines, reflow ovens, wave or selective soldering, conveyors, compressors, burn-in racks and test stations, all fed from distribution boards near the line. Load gets added faster than anyone re-engineers the feeders. Every new line or test rack goes onto the nearest board.
Where power boards fail
Most panel fires come from a small set of conditions:
- Loose or degraded terminations. Heat cycling and vibration loosen lugs, resistance rises, and the joint heats until the insulation carbonises.
- Overloaded circuits on a board sized for an earlier layout. Breakers rated for the original load trip late or never, because nobody revised the protection settings when the load went up.
- Dust, flux residue and packaging debris inside or against the enclosure. Cartons, foam and reels stored next to the board give a small arc somewhere to spread.
- Unprotected tap-offs and temporary extensions run to new test benches, usually set up during a ramp-up and never removed.
Controls an underwriter and surveyor will look for
- Infrared thermography of every distribution board and bus duct, at least once a year and after each major line addition, with hot spots logged and closed out in writing.
- Torque checks on terminations during planned shutdowns, recorded against each board.
- A current single-line diagram and load study that matches what is actually connected, with breaker settings reviewed whenever load is added.
- A clear zone around boards: no combustible storage, no WIP trolleys, no carton staging within a marked perimeter.
- Detection and suppression at the board. Smoke detection over the line and inside panel rooms, plus in-panel suppression for critical boards, reaches a fire faster than ceiling sprinklers can.
- Compartmentation between the assembly area and raw material and finished goods stores, so a line fire stays a line loss.
Note what Aditya Infotech's disclosed loss covered: raw materials, finished goods and testing equipment. A fire that starts on the line and reaches the stores and the test bay has crossed the boundaries compartmentation is supposed to hold. For a fire insurance underwriter, that is the gap between a line loss and a plant loss.
Valuing raw material, work in progress, finished goods and testing equipment
EMS claims are heavy on inventory. Components, PCBs, sub-assemblies and finished units are dense, valuable and very sensitive to smoke and heat. Each class is valued on its own basis, and the surveyor's figure is often well below the plant's first estimate because of how those bases work.
Inventory
- Raw material and components are normally indemnified at cost of replacement at the time of loss, backed by purchase invoices, the stock ledger and goods receipt records. Components bought cheaply but now on long allocation can cost more to replace. Obsolete or slow-moving stock may be written down.
- Work in progress is valued at material cost plus the labour and production overhead absorbed up to the stage it reached. That means a costing that can show where each batch was on the line, which is hard when MES and ERP records are in the same building that burned.
- Finished goods are valued at cost of production under a standard fire policy, not at selling price, unless the policy carries a specific clause for that. Any margin lost on unsold goods belongs in a business interruption claim, not the material damage claim.
Smoke and soot damage leads to many disputes. A reel that looks clean may have corrosive contamination that makes it unfit for assembly, and some OEMs will not accept components that have been through a fire at all. Get the OEM's position in writing early. The surveyor will ask for it.
Testing equipment
Test fixtures, ICT and functional testers, burn-in chambers and calibration gear are high value for their size, often imported, and often custom-built for one customer's product. Depending on how the programme was put together, they may sit in the fire policy's plant and machinery sum insured or under electronic equipment insurance. The valuation questions are reinstatement value against depreciated value, whether custom fixtures can be replaced like for like, and lead time, which drives the business interruption period more than the rebuild does.
If testing equipment is insured on a reinstatement basis, the extra over indemnity value is normally paid only once replacement is carried out. That has a direct bearing on how much of the claim can be paid on account and how much has to wait.
"Plus applicable GST": how tax sits in a loss estimate
Amber's disclosure gives the loss estimate as Rs 38.28 crore plus applicable GST. That wording separates the tax-exclusive value of the loss from the GST that would be paid to rebuild or replace it. In most commercial claims, the two are treated differently.
Why recoverable GST is normally not indemnified
A fire policy indemnifies the insured's actual loss. If a registered manufacturer buys replacement components and machinery and can claim input tax credit on the GST in those invoices, the GST is not a net cost. Paying it as part of the claim would leave the insured better off than before the fire. Surveyors therefore usually assess replacement cost net of recoverable GST and recommend settlement on that basis. GST is added back only where credit is genuinely unavailable, for example where the insured is not registered, the supply falls under a blocked category, or the business makes exempt supplies.
Where the tax can still become a loss
Netting GST out assumes the credit actually survives. Two places where it can fail:
- Reversal on destroyed goods. Section 17(5)(h) of the CGST Act, 2017 blocks input tax credit on goods lost, stolen or destroyed. Credit already taken on inputs that burned has to be reversed, and that reversal is a real cash cost. Whether the claim picks it up depends on the policy wording and on how clearly the insured documents the reversal. Raise it with the surveyor during assessment, not after the final figure is settled.
- Paperwork on the rebuild. If replacement invoices are not issued in compliant form, the credit the claim assumed is lost. Our post on the 30-day IRN clock on reinstatement invoices covers how that happens.
For finance teams, the practical step is to build two columns into the claim from day one: value excluding GST, and GST with a note on whether it is recoverable, reversed or blocked. A surveyor who gets that split up front has one less reason to hold back an interim recommendation.
The Rs 10 crore first cheque: what an on-account payment two months in signals
IL JIN's Rs 10 crore came about two months after the 4 August fire, against an estimated loss of Rs 38.28 crore. That is roughly a quarter of the tax-exclusive estimate. The disclosure says only that the final assessment is pending, so the following is a reading of what an interim payment of this kind usually implies, not a statement about this claim's internal file.
What it usually means
- Liability has been accepted. Insurers rarely release money while a coverage defence is still open. A payment on account generally means the insurer is satisfied the loss falls within the policy and that no material warranty or disclosure issue is being pursued.
- The surveyor has quantified a defensible floor. Interim payments are normally recommended in the surveyor's interim report against heads that are already verified: debris removal, clearly destroyed stock with invoice support, or plant beyond repair. A payment of about a quarter of the estimate is consistent with paying the undisputed part and leaving valuation arguments for later.
- The rest is still being worked through. In an EMS loss, the open items are usually salvage on smoke-affected components, WIP costing, reinstatement on test equipment, and customer-owned stock.
What it does not mean
An on-account payment does not confirm the final figure, and it is not a percentage that will be applied to the whole claim. The final settlement can come in above or below the disclosed estimate once salvage, depreciation, underinsurance and GST are worked through.
Our guide to on-account and interim payments in large property claims covers how to structure the request. The point here is narrower. For a listed EMS company, the first cheque is worth disclosing because it tells investors the insurer has accepted the claim in principle, and that changes how the rest of the claim will be handled.
Between the first cheque and the final assessment
The period after an interim payment is where large claims either close cleanly or drag on. For an electronics plant, the work falls into a few streams.
- Close out salvage on contaminated inventory. Agree a protocol with the surveyor for testing smoke-exposed reels and boards, decide what is scrapped and what is cleaned and requalified, and get the scrap sold with documentation. Undecided salvage is the most common reason a final report stalls.
- Rebuild the WIP costing. Reconstruct batch status from MES backups, customer delivery schedules and production logs. The surveyor needs to see where each lot was on the line, not a total.
- Separate owned and customer-owned stock. Where customer consignments burned, decide who claims and under which policy before the final figures are agreed. This is the subject of our earlier Amber post, so we do not repeat it here.
- Decide on reinstatement of testing equipment. If the policy pays reinstatement only after replacement, placing orders for long-lead testers is both an operational and a claim decision. Delay costs production and holds back the reinstatement portion of the claim.
- Document the GST position line by line. Show what credit was reversed on destroyed inputs and what will be claimed on replacements, so the GST question is settled on evidence rather than assumption.
- Request further on-account payments as heads close. There is no rule against a second or third interim release. Each time a head is fully verified, ask for it to be paid.
What EMS manufacturers should fix before the next loss
Both fires were at subsidiaries of well-capitalised groups that said they were adequately insured. The lessons apply equally to mid-sized EMS and component makers, who are less able to absorb a long wait for settlement.
- Electrical: annual thermography on every board, re-study of load and protection after each line addition, clear zones around panels, detection inside panel rooms.
- Layout: fire separation between assembly, test and stores, so one ignition does not take raw material, finished goods and testers together.
- Sums insured: stock declared or insured on a basis that tracks peak inventory during production ramps, with WIP and finished goods covered at cost and testing equipment on reinstatement value.
- Records: ERP, MES and costing data backed up off-site, so WIP and stock can be reconstructed without the building.
- GST: a standing note from finance on which inputs carry credit, so a claim can be presented net of recoverable tax from day one.
- Programme fit: check whether testing equipment belongs in the fire policy or under electronic equipment cover, and whether business interruption cover reflects realistic lead times for custom test fixtures. Our electronics component plant risk profile covers the wider exposure.
A disclosed loss estimate is the opening figure in a claim, and a first interim cheque marks the point where the insurer has accepted it. What the insured gets at the end depends mostly on the records and controls in place before the fire.